Ayr Arena

The Challenge:

This arena project was pre-tendered prior to the construction drawings being completed, which meant we did not have the specs to work with. At the same time, we had to work in conjunction with multiple disciplines and stakeholders including the general contractor and the project’s architect. Scheduling and safety issues were also paramount.

The Grassmere Solution:

We self-performed the work through our “sister” erection company, KDM Erectors.

The Result:

The project was completed safely, on time and within budget.

Let’s Discuss Your Project. Request a Consultation Today!

Basic Specifications:

Client: Ayr Arena
Location: Ayr, ON
Project Description: Supply and erect an arena complex
Construction Services: Bid Spec, evolved into Pre-Engineered building
Sector Served: Institutional
Project Completion Date: September, 2011


Total Square Feet: 36,000
Structural Systems: Butler Pre-Engineered Building
Roof System: MR-24® standing seam
Roof Insulation Type and Thickness: Metal Building Insulation (MBI) with an upgraded Arena Shield Facing
Wall System: N/A
Wall Insulation Type and Thickness: N/A