The Challenge:

Ayr, ON

This arena project was pre-tendered prior to the construction drawings being completed, which meant we did not have the specs to work with. At the same time, we had to work in conjunction with multiple disciplines and stakeholders including the general contractor and the project’s architect. Scheduling and safety issues were also paramount.

The Grassmere Solution:

We self-performed the work through our “sister” erection company, KDM Erectors.

The Result:

The project was completed safely, on time and within budget.

Basic Specifications:

Client:

Ayr Arena

Location:

Ayr, ON

Project Description:

Supply and erect an arena complex

Construction Services:

Bid Spec, evolved into Pre-Engineered building

Sector Served:

Institutional

Completion Date:

September, 2011

Total Square Feet:

36,000

Structural Systems:

Butler Pre-Engineered Building

Roof System:

MR-24® standing seam

Roof Insulation Type and Thickness:

Metal Building Insulation (MBI) with an upgraded Arena Shield Facing

Share on facebook
Facebook
Share on twitter
Twitter
Share on linkedin
LinkedIn

Let’s Discuss Your Project. Request a Consultation Today!

Completed Projects

Working with the church’s board of directors, the challenge was...

Grassmere was awarded a contract by the Long Point Region...

This arena project was pre-tendered prior to the construction drawings...

This project comprised an administration office as well as multi-tenant...

Start your Project Today

Request a Consultation